Paramount
Helical Tie Down Anchors

312 Tie Down Anchors Through Dense Stone Columns to Resolve Buoyancy Challenges, 1 Week Ahead of Schedule
Richmond, BC
July 2019

A new development by Oriental Yuhong (Canada) Developments Ltd. proposed to build a commercial and residential multi-use mixed tower development at 6340 No. 3 Road in Richmond. A total of 4 11-15 story buildings are to be developed over top of 2 levels of underground parking. TerraCana and Rush Contracting decided to team up and provide a solution for the foundation requirements.

The Challenge

The project site presented a few challenges. Previously, the site received stone columns to increase the soil density. So this meant that we had to install our anchors through the dense soils. As well as in some cases being installed directly through the stone columns. Another challenge faced was the level of the water table in Richmond, which created the challenge of bouyancy controls. Especially with the varying loads over the entire slab. Another challenge was coordinating work with the multiple other trades working inside of the excavation.

The Solution

TerraCana was responsible for the design, testing, and installation of the tie down anchors. This resolved the buoyancy challenges and uneven loads over the raft slab. Additionally, we also conducted tests on 5% of all production piles. Our team has had extensive experience installing tie down anchors in soils with a large range of densities. Our foreman coordinated work with other contractors on site allowing him to complete installation 1 week ahead of schedule. The raft slab is now ready to support the new buildings.

The Outcome

TerraCana completed installation 1 week ahead of schedule, resolving buoyancy challenges and delivering a raft slab ready to support 4 mixed-use towers over 2 levels of underground parking.

Technical Specifications

No. of Piles
312
Pile Type
7 inch diameter helical anchors
Application
Commercial
Testing
5% of all production piles tested

Key Outcomes

Installation completed 1 week ahead of schedule
Buoyancy challenges resolved with tie down anchor design
Anchors successfully installed through dense stone columns

Project Partners

General Contractor

Equipment

Anchor Installation
John Deere 225D

Richmond, BC