Foundation Specialists - British Columbia
604-270-4773
info@terracana.ca
32Micropiles Installed·120 m³Concrete Poured·ZeroTrain Delays·3 WeeksAhead of Schedule·500+Concrete Dowels·109 yrBridge Age·32Micropiles Installed·120 m³Concrete Poured·ZeroTrain Delays·3 WeeksAhead of Schedule·500+Concrete Dowels·109 yrBridge Age·

Hawkes Creek Bridge
Foundation Rehabilitation

Micropile Underpinning for a 109-Year-Old Rail Bridge
Williams Lake, BC
Jan – Jun 2025

The Hawkes Creek Bridge required foundation rehabilitation after years of active foundation movement threatened the structural integrity of one of Canada’s tallest rail bridges. Located 25 km north of Williams Lake in remote BC terrain, TerraCana delivered micropile underpinning, concrete rehabilitation, and sheet pile shoring — completing the project three weeks ahead of schedule without a single train shutdown or delay.

The Challenge

The Hawkes Creek Bridge, a 254-foot-tall structure and one of the tallest rail bridges in Canada, had experienced active foundation movement over several years. At 109 years old, the bridge required foundation rehabilitation to halt ongoing structural displacement while remaining fully operational for active rail traffic.

Access was the defining challenge. The bridge sits in remote terrain 25 km north of Williams Lake with no conventional site access. CN’s original plan called for accessing the site via the rail line itself.

Working beneath an active rail bridge at nearly 300 feet in height, in the middle of a BC winter with temperatures dropping below 30 degrees Celsius, demanded a solution that addressed logistics as much as engineering.

The Solution

TerraCana developed an alternative access strategy, working with a local landowner to approach the site overland rather than via the rail line. The team built a roadway through pastures to the top of the bridge, then constructed switchback access roads down to the base of the nearly 300-foot-tall structure — all through extreme winter conditions. Progressive Ventures completed the access road construction.

With access established, TerraCana installed sheet pile shoring to stabilize the steep slope and allow excavation of the existing footings. Over 500 dowel holes were drilled 3 feet deep into the existing concrete, followed by installation of 32 micropiles at 20 metres long with 7.5-metre permanent steel casings. KCB served as both the structural and geotechnical engineer, while Structec engineered the temporary work pads.

Concrete placement presented its own logistical challenge. The site sat an hour from town, leaving only one hour of working time after the two-hour placement window. TerraCana brought in Sustainable Concrete to set up an on-site batch plant, effectively doubling the available working time. Concrete was transported down the switchback roads in tracked Morooka carriers, loaded into a crane bucket, and poured into forms — 120 cubic metres total. Harris Rebar handled all concrete reinforcing, and Cashmere Concrete completed the formwork.

A rigorous vibration and bridge movement monitoring program ran throughout construction to protect the active structure.

The Outcome

TerraCana’s alternative access strategy eliminated the need for rail shutdowns — not a single train was delayed over the entire project. The foundation rehabilitation halted the active movement that had threatened the bridge for years. On a five-month schedule, the project finished three weeks early.

Technical Specifications

Micropiles
32 micropiles, 20 m long, 7.5 m permanent steel casing
Concrete Dowels
500+ dowels, 3 feet into existing concrete
Concrete Volume
120 cubic metres, on-site batch plant
Shoring
Sheet pile, slope stabilization
Crew Size
4 to 8 TerraCana crew on site
Schedule
Completed 3 weeks ahead of schedule

Key Outcomes

Zero train shutdowns or delays
Finished 3 weeks ahead of schedule
Active foundation movement halted

Project Partners

Structural and Geotechnical Engineer
Temporary Works Engineer
Access Road Construction
Concrete Supply

Equipment

Access and Shoring
Hitachi 345 Excavator with Movax
Micropile Drilling
SoilMec SM22
Material Transport
Morooka 1200 tracked carriers

Williams Lake, BC

Working on a similar project?

Get a quote from TerraCana’s engineering team.

More Projects